Date | Proposal |
June 2024 | Tenders invited from suitable contractors |
July - August 2024 | Tenders received and shortlist of suitable contractors be considered |
August – September 2024 |
Public Consultation Final designs and contractor to be approved
|
October – November 2024 | Work to commence |
Due to the costs received to undertake the work the Town Council decided to reduce the scope of the work to undertake in order of urgent priority as follows:
Vehicular Culvert Bridge |
High Priority |
Drainage repair work to car park entrance |
High Priority |
Work to brook bank |
Medium Priority |
Drainage work down Lubbesthorpe Bridle Path |
Medium Priority |
Tarmac and work to car park surface |
Low Priority |
The two high priority works as shown in the table above have been approved by the Policy & Resources committee on 12th September, to be undertaken, subject to funding.
The work has been reduced considerably due to the initial costs we received to do the full works we wanted to do.
Now we want to hear from you!
Does the proposed Flood Alleviation work need undertaking?
Should the Town Council be undertaking this Flood Alleviation work at this time?
Do you agree with the priority order of the work to be undertaken?
Head over to our Consultation page for further information and how to share your thoughts on this project with us!
Closing date for comments to be Wednesday 31st October 2024